DTE Electric Company’s Application grant ex parte approval for Cedar Fields Solar Park Project and supporting Exhibit 1 the Affidavit of Luisa M. Dunlap, Attachment A Module MSA - DTE Electric Company between New East Solar Energy (redacted) and the EPC MSA - DTE Electric Company between Burns and McDonnell (redacted), Exhibit 2 the Affidavit of Ralph Luciani, the Attachment B DTE 2023 Renewable Energy Request for Proposals Report.
Overview
DTE Electric applied for ex parte approval of its 138 MW Cedar Fields Solar Park project and associated module and EPC master service agreements as consistent with its approved IRP in Case U-21193, supported by affidavits and a 2023 renewable energy RFP report.
Key Points
- •Seeks ex parte approval under MCL 460.6t, 460.6j, and 2008 PA 295
- •Cedar Fields Solar Park to be located in Clare and Gladwin Counties, interconnecting at Cedar Fields substation
- •Project nameplate capacity anticipated at 138 MWAC
- •DTE executed a module supply MSA with New East Solar Energy and an EPC MSA with Burns & McDonnell
- •Project arose from DTE’s 2023 competitive renewable energy RFP monitored by Guidehouse
DTE Electric Company’s Application grant ex parte approval for Cedar Fields Solar Park Project and supporting Exhibit 1 the Affidavit of Luisa M. Dunlap, Attachment A Module MSA - DTE Electric Company between New East Solar Energy (redacted) and the EPC MSA - DTE Electric Company between Burns and McDonnell (redacted), Exhibit 2 the Affidavit of Ralph Luciani, the Attachment B DTE 2023 Renewable Energy Request for Proposals Report.
- Category
- APPApplications
- Subcategory
- APP-EXPEx Parte Application
- Party Type
- Company
- Confidentiality
- Redacted
- Filing Date
- June 27, 2024
- Case Number
- U-21193
- Filed By
- Andrea E. Hayden
- Pages