U-21193-0535
Approves the application
AI-Generated Summary
Confidence: 94%
Overview
The Michigan Public Service Commission approved DTE Electric’s ex parte application for the Cedar Fields Solar Park Project and related solar EPC and module supply contracts as consistent with its approved 2022 integrated resource plan.
Key Points
- •Commission approved Cedar Fields Solar Park as an IRP resource
- •Approved associated EPC Master Service and solar module supply agreements
- •Found project costs, including $2,108/kW installed and $70/MWh LCOE, reasonable and below the 150% IRP threshold
- •Authorized cost recovery through renewable energy plan revenue recovery mechanism, transfer price mechanism, and related surcharges
- •Project is expected to receive a 30% ITC plus 10% Energy Community bonus and to reach COD in Q2 2027 due to interconnection delays
Filing Description
Approves the application
Classification
Confidence: 93%
- Category
- COMCommission Actions
- Subcategory
- COM-APRApproval Order
- Party Type
- Unknown
- Confidentiality
- Public
Document
Quick Actions
Filing Details
- Filing Date
- September 5, 2024
- Case Number
- U-21193
- Filed By
- Michigan Public Service Commission
- Pages
- 13
- File Size
- 550.0 KB
Processing Info
- Classified
- March 28, 2026
- Summarized
- February 6, 2026
- Indexed
- February 3, 2026